B51 Mauritz trough, 3rd construction phase
Location:
Minster
Completion:
2026
B51 Mauritz trough, 3rd construction phase
Location B51 at Pleistermühlenweg in Münster
Expansion and new construction of the Münster bypass
As a heavily used motorway, the B51 is of considerable supra-regional importance for the greater Münster area. It is also part of the supra-regional B51/B64 Münster – Warendorf – Rheda-Wiedenbrück traffic axis.
The stretch of the B51 in the Münster bypass section has existed since the 1960s. Traffic congestion was already inevitable in 1965. The first two sections were upgraded between 1990 and 2001. Since 2015, work has been underway on the current third section and the extension northwards as the B481.
The expansion of the B51 became necessary because the federal highway, which currently has two lanes, was no longer sufficient to meet requirements and was causing considerable inconvenience to local residents and road users due to noise and traffic displacement in the adjacent residential areas.
Around 210 million euros are being invested in the federal budget for the bypass. Over the total distance of 6.2 kilometers, 17 new bridges, over 5.6 kilometers of noise barriers and three trough structures will be built.
The work has progressed so far that the next milestones are also firmly planned: In 2026, work on the 900-metre-long trough structure in the expansion section of the B51 should be so far advanced that this construction section will be available for traffic.
The four-lane expansion of the B51 over a length of 2.6 kilometers and the new construction of the B481 over a length of a good 4.6 kilometers as well as the connection to the L587 (Schifffahrter Damm) will create a continuous south-east bypass for the city of Münster. In future, the bypass will provide an efficient link from the MS Süd junction to the A1 Greven junction, which will also be able to cope with future traffic loads and relieve the burden on residential areas and the urban road network.
The project is aiming for DGNB "Sustainable Construction Site" certification from the German Sustainable Building Council.
-
Characteristics
- Built-up area (BF): ≈ 24,000 m²
Road construction: - Excavation pit excavation and intermediate transportation: ≈ 120,000 m³
- Road surface demolition: ≈ 9,500 m³
- Lay DN 250-600 pipelines: ≈ 1,200 m
- Frost protection layer 0/45: ≈ 8,000 m³
- Asphalt work: ≈ 21,000 m²
Reinforced concrete construction - Trough structure - length: 905 m
- Trough structure - width (var.): 24.10 - 29.50 m
- Cleanliness layer: ≈ 23,000 m²
- Concrete: ≈ 35,000 m³
- Reinforcing steel: ≈ 3,600 t
- Pipes DN 300 to DN 500: ≈ 1,440 m
- Installing anchors for steelwork ≈ 2,300 pcs
Steel construction - Steel structures for bridge superstructures: ≈ 58 t
- Built-up area (BF): ≈ 24,000 m²
-
Construction time
- Total construction time vs. 03.2023 to 03.2026
- Reinforced concrete construction work vs. 09.2023 to 07.2025
-
Construction site regular operation
- Monday to Friday 07:00 to 18:00
- There is generally no work on Saturdays, Sundays and public holidays.
Certified by the German Sustainable Building Council (DGNB)
Ed. Züblin AG is pursuing several goals with this project: A sustainable construction site organisation, the conservation of resources as well as the minimisation of emissions, responsibility for the health and well-being of the builders, the cultivation of good neighbourliness and, of course, high-quality construction. For this, Ed. Züblin AG was the first company to be recognised by the German Sustainable Building Council (DGNB).
Here you can find more information about the DGNB system for sustainable construction sites: https://www.dgnb.de/en/certification/buildings/construction-site
Selected measures in the project
-
Energy management in construction
Construction site investigations and comparative considerations for the most energy-efficient project execution possible. For example, selection of a large concrete bucket to reduce the number of lifts.
-
Saving resources and reducing emissions through LEAN Construction
As part of the lean approach, a production plan with call-off dates was drawn up. Construction production planning is detailed on a weekly basis and adapted to actual production progress. Changes from the construction process are taken into account on an ongoing basis and just-in-time deliveries can be better implemented. Repeat orders and new orders due to late changes to the plan are avoided.
-
Concepts for reducing the environmental impact and pollution caused by the construction site
The project is located in the immediate vicinity of adjacent residential buildings, so efforts are being made to avoid or reduce the impact of the construction site as much as possible. The concepts for avoiding noise and dust on the construction site are key areas of action. There are also concepts for waste avoidance and an environmentally and resident-oriented logistics concept.
-
Steel construction
The supporting structures of the two pedestrian bridges are planned as steel constructions. This enables a high degree of prefabrication and reduces the construction time.
-
Regional construction partners
Regional companies are involved in the provision of services.
| Certification contact person | Kristina Pors (Züblin), Sven Bachner (STRABAG) |
| Project contact | Christian Pöppinghaus |
| Construction site address | B51 level with Pleistermühlenweg 48155 Münster Phone +49 203-2820301 Subdivision NRW Secretariat Unit Civil Engineering |
| Download | Press release |
| Link | DGNB: Certification Roads.NRW |