Pandion Rise and Next
Location:
Düsseldorf
Completion:
2024
Pandion Rise and Next Düsseldorf
Location Völklingerstraße 2 in Düsseldorf
Pandion Rise and Next Düsseldorf is a mixed-use building complex consisting of apartments, a daycare center and a 17-storey office tower with some gastronomic use.
The project is aiming for DGNB "Sustainable Building Site" certification from the German Sustainable Building Council.
-
Characteristics
- Pandion Rise:
Gross cubic capacity (BRI): 235,362 m³ - Gross floor area (GFA): 60,178 m²
- Gross floor area (GFA): approx. 11,380 m²
- Above ground: 17 storeys
- Underground: 2 storeys
- Pandion Next:
Plot area (GF): 5,820 m² - Gross cubic capacity (BRI): 73,022 m³
- Gross floor area (GFA): 23,148 m²
- Above ground: 5 storeys
- Underground: 2 storeys
- Pandion Rise:
-
Construction time
- Earthworks from September 2022 to April 2024
- Shell construction from September 2022 to June 2024
- Completion (shell) June 2024
-
Construction site regular operation
- Monday to Friday 07:00 to 18:00
- Saturday 07:00 to 14:00
- There is generally no work on Sundays and public holidays.
Certified by the German Sustainable Building Council (DGNB)
Ed. Züblin AG is pursuing several goals with this project: A sustainable construction site organization, the conservation of resources as well as the minimization of emissions, responsibility for the health and well-being of the builders, the cultivation of good neighbourliness and, of course, high-quality construction. For this, Ed. Züblin AG was the first company to be recognized by the German Sustainable Building Council (DGNB).
Here you can find more information about the DGNB system for sustainable construction sites: https://www.dgnb.de/en/certification/buildings/construction-site
Selected measures in the project
-
Saving resources and reducing emissions through LEAN Construction
As part of the lean approach, a production plan with call-off dates (e.g. insulation) was created. Construction production planning is detailed on a weekly basis and adapted to actual production progress. Changes in the construction process are constantly taken into account and just-in-time deliveries can be better implemented. Repeat orders and new orders due to late changes to the plan are avoided.
-
Measures to prevent pollution from the construction site
The project is located in a high-density inner city area, so that the impact of the construction site is avoided or reduced as far as possible. Particularly noteworthy are the efforts to protect trees and soil and, due to the lack of space, the high requirements for securing public footpaths at the construction fence.
-
Energy management in construction
These include operational construction studies and comparative considerations for the most energy-efficient project execution possible. For example, the selection of a large concrete bucket to reduce the number of lifts comes into play here.
| Certification contact person | Kristina Pors |
| Project contact | Sanja Kokovic |
| Construction site address | Völklingerstrasse 2 40219 Düsseldorf Phone +49 211 5996-214 Züblin Subdivision NRW Management assistant Düsseldorf unit |
| Download | Press release |
| Link | DGNB: Certification |