Sports hall at the Hildegard von Bingen Grammar School
Sports hall at the Hildegard von Bingen Grammar School © Moritz Falkenhain/ ZÜBLIN

Hildegard von Bingen Grammar School

Location: 
Cologne

Build time: 
2023–2025

Client: 
City of Cologne Buildings Management Department

Back to Projects

Hildegard von Bingen Grammar School

ZÜBLIN is carrying out a comprehensive refurbishment and conversion of a listed sports hall, as well as the construction of a new extension, at the Hildegard von Bingen Gymnasium in Cologne.

On behalf of the City of Cologne’s Building Management Department, the Existing Buildings Division of the NRW Directorate carried out the refurbishment and conversion of the Hildegard von Bingen School in the Sülz district as the main contractor. Built around 1960, the school comprises three interconnected building wings, each with three or two storeys. Adjacent to these are the assembly hall, the former sports hall and a new building housing a sports hall on the site.  As part of the refurbishment, the former sports hall was converted into a canteen with all-day facilities. This provides space for around 200 pupils, as well as a fully equipped kitchen, storage areas and staff rooms for the catering staff.

Before the refurbishment work began, the building was inspected for hazardous substances and concrete damage. The hazardous substances identified during the analysis were professionally removed and disposed of. The significant concrete damage was also treated and repaired.

Particular attention was also paid to the building’s listed status, which has been in force here since 1980. In preparation for this, samples were taken from the building and analysed in order to reconstruct the original colour tones and materials. On this basis, the entire refurbishment was planned and carried out in close consultation with the heritage authority.

To preserve the external appearance of the school building, the façade elements were painted in the original colours and a glass block façade in the style of the 1960s was erected. A further requirement of the heritage protection regulations was that technical roof installations, such as ventilation units, must not be positioned on the roof. To achieve this, a mezzanine floor made of exposed concrete was installed in the former sports hall. This adjoins an external wall on one side and is otherwise supported by internal partition walls, so as not to obstruct the view of the skylights. These were removed, treated for contaminants and structurally refurbished, and then reinstalled. The former wooden impact wall was also removed, refurbished and reassembled plank by plank in accordance with heritage conservation guidelines. This ensures that the characteristic features of the former gymnasium remain evident. In addition to preserving the old wall cladding, the new partition walls in exposed concrete complement the interior appearance.

Alongside the work on the building, the outdoor facilities are being refurbished. The school’s main entrance is being refurbished, whilst the layout of the mosaic and paving areas will remain unchanged due to heritage protection requirements. Additionally, raised beds complete the overall look of the main entrance. During the works, care was also taken to protect the existing trees and their roots, in close collaboration with the Parks Department. Further areas of the school playground are also being refurbished and will in future offer pupils opportunities to play, spend time outdoors and store their bicycles.

The scope of works is completed by the installation of several infiltration systems within the outdoor areas. Through infiltration trenches, rainwater seeps into the groundwater and does not need to be discharged into the sewer system.

The project was certified as a ‘Sustainable Construction Site’ in accordance with the criteria of the German Sustainable Building Council (DGNB).

  • Key figures
    • Plot area (GF): 1,052.50 m²
    • Gross internal volume (GIV): 5,324.00 m³
    • Gross floor area (GFA): 1,324.00 m²
    • Upper floors: 2 storeys
    • Basements: 1 storey
  • Construction period
    • Structural work from November 2023 to February 2025
    • Outdoor facilities from June 2024 to September 2025
    • Completion of the building: June 2025
  • Standard operating procedures for construction sites
    • Monday to Friday, 7.00 am to 5.00 pm
    • Saturday (if required) 7.00 am to 3.00 pm
    • As a rule, no work takes place on Sundays and public holidays.

Certified by the German Sustainable Building Council (DGNB)

Ed. Züblin AG is pursuing several objectives with this project: sustainable site organisation, the conservation of resources and the minimisation of emissions, responsibility for the health and wellbeing of construction workers, fostering good neighbourly relations and, of course, high-quality construction work. For this, Ed. Züblin AG was the first company to receive an award from the German Sustainable Building Council (DGNB).

You can find further information on the DGNB system for sustainable construction sites here: https://www.dgnb-system.de/de/gebaeude/baustelle/

Selected measures within the project

  • Production planning using LEAN Construction

    As part of the lean approach, a production plan with call-off dates – for example, for concrete – was drawn up. Construction production planning was carried out in detail on a weekly basis and adjusted to reflect actual production progress. Changes arising from the construction process were taken into account on an ongoing basis, which improved the implementation of just-in-time deliveries. This made it possible to avoid back-orders and new orders resulting from subsequent changes to the schedule.

  • Noise prevention measures

    The work was carried out within the existing building. To ensure that school operations were not disrupted, the work was carried out in close consultation with the school management.

  • Quality assurance of construction products used

    The materials and construction products used and installed were assessed for compliance with the list of construction products to be evaluated, drawn up by the City of Cologne. The assessment and evaluation of the construction products focused on their health compatibility with regard to the building’s users. The assessment was carried out in accordance with the requirements defined by the City of Cologne.

Certification contact person Kristina Pors
Project contact Markus Lubnau,
Manfred Thiemann
Construction site address Leybergstraße 1
50939 Cologne

Ed. Züblin AG; Subdivision NRW, 
Unit Renovation of existing buildings
Download Press release
Link DGNB: Certification