Struenseestraße School Campus in Hamburg Altona – Entrance area
Struenseestraße School Campus in Hamburg Altona – Entrance area © Daniel Sumesgutner

Struenseestraße School Campus

Location: 
Hamburg Altona

Build time: 
February 2022 – September 2026

Client: 
SBH | School Construction Hamburg

Back to Projects

Struenseestraße 20–32 School Campus in Hamburg Altona

The Struenseestraße school campus is being built between Königstraße and Struenseestraße. The construction project involves the erection of four buildings.

The Struenseestraße School Campus is one of the largest and most ambitious construction projects ever undertaken as part of Hamburg’s school-building programme.
On the school site, which covers approximately 28,500 square metres, the Struenseestraße School Campus consortium (Ed. Züblin AG and OTTO WULFF GmbH) built three new schools on the approximately 28,500 square metre school site on behalf of SBH | Schulbau Hamburg, with capacity for over 2,000 pupils and 250 teaching staff. These are the Struensee Gymnasium, the German-French Gymnasium and the ‘An der Elbe’ all-day school, complete with associated sports halls.
Of central importance to the Struenseestraße school campus are the communal and all-day areas, which are set to serve as the ‘heart’ of the new school campus in future. The grammar school building includes a canteen in the basement with capacity for around 400 people. A canteen serving around 60 people is planned for the all-day school.

Subdivision:
The project is aiming for DGNB ‘Sustainable Construction Site’ certification from the German Sustainable Building Council.
  • Key figures
    • Site area (GF): 28,500 m²
    • Built-up area (BF): 7,444 m²
    • Gross internal volume (GIV): 136,772 m³
    • Gross floor area (GFA): 29,335 m²
    • Above ground: 4 storeys
    • Basement: 1 floor
  • Construction period
    • Structural work from August 2023 to August 2024
    • Building envelope from January 2024 to January 2025
    • Extension from January 2024 to March 2025
    • Outdoor facilities from May 2024 to April 2025
    • Completion: May 2025
  • Standard operating procedures for construction sites
    • Monday to Friday, 7.00 am to 7.00 pm
    • Saturday, 7.00 am to 3.00 pm
    • As a rule, no work takes place on Sundays and public holidays.

Certified by the German Sustainable Building Council (DGNB)

Ed. Züblin AG is pursuing several objectives with this project: sustainable site organisation, the conservation of resources and the minimisation of emissions, responsibility for the health and wellbeing of construction workers, fostering good neighbourly relations and, of course, high-quality construction work. For this, Ed. Züblin AG was the first company to receive an award from the German Sustainable Building Council (DGNB).

You can find further information on the DGNB system for sustainable construction sites here: https://www.dgnb-system.de/de/gebaeude/baustelle/

Selected measures within the project

  • Measures to minimise disruption caused by the building site

    A range of measures, including those relating to noise and dust prevention and logistics, ensure that the impact on local residents is kept to a minimum. Similarly, a waste prevention strategy ensures that as much material as possible is channelled into the circular economy.

  • Staff

    An employee of the main contractor monitors compliance with the sustainability policies and provides training to subcontractors.

  • Prefabricated components

    The extensive use of prefabricated components (openwork ceilings, hollow walls, parapets, columns, beams and staircases) enables a shorter construction period. Similarly, the volume of waste is reduced thanks to the pre-assembled components.

  • Resource conservation and emissions reduction through LEAN Construction

    As part of the lean approach, a production plan with call-off dates (e.g. insulation) was drawn up. Construction production planning is detailed on a weekly basis and adjusted to reflect actual production progress. Changes arising from the construction process are taken into account on an ongoing basis, and just-in-time deliveries can be implemented more effectively.

Certification contact person Kai Zimmermann
Project contact Sabine Detlefsen
Construction site address Struenseestraße 20–32
22767 Hamburg

Tel. +49 40 20208-1001
Züblin Northern Regional Office
Assistant to the Head of Division
SF Hamburg, Mecklenburg-Western Pomerania
Download Press release
Link DGNB: Certification
School building in Hamburg